Extracted from this filing and checked against the source text.
Restructurings & Charges
SEC 8-K Item 2.05/2.06
confidence 0.95
FMC CORP announced a restructuring with charges of Pre-tax restructuring charges in the range of approximately $180 to $215 million in connection with Project Focus affecting Global (Global workforce reduction of approximately 8%).
- Type
- restructuring
- Charge
- Pre-tax restructuring charges in the range of approximately $180 to $215 million in connection with Project Focus
- Affected area
- Global
- Headcount
- Global workforce reduction of approximately 8%
Exact text from the filing
The Company expects to incur pre-tax restructuring charges in the range of approximately $180 to $215 million, which is subject to future changes, in connection with Project Focus.
View on SEC.gov
Restructurings & Charges
SEC 8-K Item 2.05/2.06
confidence 0.9
FMC CORP announced a restructuring with charges of Consulting and other professional service fees totaling approximately $5 to $15 million affecting Global (Global workforce reduction of approximately 8%).
- Type
- restructuring
- Charge
- Consulting and other professional service fees totaling approximately $5 to $15 million
- Affected area
- Global
- Headcount
- Global workforce reduction of approximately 8%
Exact text from the filing
The Company expects to incur consulting and other professional service fees totaling approximately $5 to $15 million to help execute these actions as well as for the design and implementation of the future structures and processes.
View on SEC.gov
Restructurings & Charges
SEC 8-K Item 2.05/2.06
confidence 0.85
FMC CORP announced a restructuring with charges of Asset write-off charges in the range of $80 to $90 million primarily related to possible relocation of manufacturing and other operations affecting Global (Global workforce reduction of approximately 8%).
- Type
- restructuring
- Charge
- Asset write-off charges in the range of $80 to $90 million primarily related to possible relocation of manufacturing and other operations
- Affected area
- Global
- Headcount
- Global workforce reduction of approximately 8%
Exact text from the filing
We expect asset write-off charges in the range of $80 to $90 million in connection with Project Focus activities primarily related to the possible relocation of certain manufacturing and other operations.
View on SEC.gov
Restructurings & Charges
SEC 8-K Item 2.05/2.06
confidence 0.95
FMC CORP announced a restructuring with charges of Total severance charges and related benefit costs estimated in the range of $85 to $100 million affecting Global (including voluntary separation program in select jurisdictions and workforce reduction in Brazil) (Global workforce reduction of approximately 8%).
- Type
- restructuring
- Charge
- Total severance charges and related benefit costs estimated in the range of $85 to $100 million
- Affected area
- Global (including voluntary separation program in select jurisdictions and workforce reduction in Brazil)
- Headcount
- Global workforce reduction of approximately 8%
Exact text from the filing
The Company estimates total severance charges and related benefit costs for actions associated with Project Focus to be in the range of $85 to $100 million.