WEC Energy Group delays retirement of Oak Creek coal units by 1-1.5 years; Columbia units to 2026
WISCONSIN ELECTRIC POWER CO
- Oak Creek Units 5/6 delayed to May 2024; Units 7/8 to late 2025 (approx 18 months).
- Columbia Energy Center units now retired by June 1, 2026 (previously 2023/2024); WPS owns 300 MW (27.5%).
- Reasons cited: tight Midwest power supply and supply chain delays for renewable projects.
- No significant new capital needed; company reaffirms CO2 reduction targets of 60% by 2025 and 80% by 2030 vs 2005.
- Total capacity of Oak Creek older units is 1,100 megawatts.