other material
confidence high
sentiment neutral
materiality 0.70
TETRA enters construction MSA for Phases 2/3 of Arkansas bromine project; $95M expected cost
TETRA TECHNOLOGIES INC
- Subsidiary TETRA Bromine Project LLC signed MSA with Diversified Construction & Design for construction of Phases 2 and 3.
- Estimated remaining capex $220M as of March 31, 2026; ~$95M expected under this agreement.
- Liquidated damages for delay capped at $2M; warranty period 18 months after final acceptance, not beyond Dec 31, 2029.
- Work orders to define scope, price (fixed-price or rate basis), and schedule per MSA terms.
- TBP may terminate without cause on 30 days' notice, paying demobilization costs plus 5% of unpaid contract price.