Lithium Americas reports Q1 net loss $11.5M; Thacker Pass construction begins with first concrete in May 2025
LITHIUM AMERICAS CORP.
2025-Q1 EPS reported
-$0.05
- Net loss $11.5M ($0.05/share) vs $6.3M ($0.04/share) in Q1 2024; increase due to higher G&A and transaction costs.
- Cash and restricted cash $446.9M at Mar 31, 2025; closed $250M Orion investment and GM FID ($100M from GM, $191.6M from LAC) post-quarter.
- Major construction at Thacker Pass started; first permanent concrete placed early May 2025; completion of Phase 1 targeted late 2027.
- Expect first draw on $2.26B DOE loan in Q3 2025; detailed engineering >60% complete, targeting >90% by year-end.
- 75% of project cost structure (labor, contractors, services) not expected to be directly affected by tariffs.