EchoStar renegotiates Jupiter 3 satellite contract with Maxar, securing financial concessions and delay protections.
EchoStar CORP
- Amendment waives approximately $14M in payments through orbit-raising and $44.5M (plus 6% interest) in deferred in-orbit incentives.
- Maxar must pay additional liquidated damages for further delays: $8M/month from July 2023, rising to $10M/month from October 2023.
- EchoStar gains termination right if Jupiter 3 satellite not delivered by January 1, 2024, with refund provisions.
- EchoStar to provide services to Maxar in 2023 for at least $30M margin under a separate agreement.
- Launch of the Jupiter 3 satellite still expected in the first half of 2023 based on current Maxar schedule.