Plug Power signs $132.5M-$142M asset sale to Stream Data Centers, first step of $275M liquidity plan
PLUG POWER INC
- Sale of Project Gateway site in New York for gross proceeds of at least $132.5M, up to $142M depending on conditions; $6M deposit from Stream.
- Part of a $275M+ liquidity initiative through asset monetization, restricted cash release, and reduced maintenance expenses.
- Transaction expected to close by June 30, 2026, subject to customary closing conditions.
- Two additional optimization initiatives expected in 2026 to complete the $275M total.
- Plug focuses on hydrogen production and fuel cell deployment; Stream to develop hyperscale data center at STAMP park.