Ivanhoe Electric signs $64.7M definitive TBM purchase agreement for Santa Cruz Copper Project
Ivanhoe Electric Inc.
- Total purchase price $64.7M for tunnel boring machine from Robbins; $1.1M deposit already paid.
- Remaining $63.6M due in milestones: 20% after signing, 32.5% at shipping, 20% at delivery, 27.5% at commissioning.
- Commissioning target July 30, 2027; liquidated damages $50,000 per calendar day for delay caused by Robbins.
- Agreement signed May 28, 2026; TBM will bore the mine decline tunnel at Santa Cruz Copper Project near Casa Grande, AZ.
- Assembly costs of $5.8M paid separately; title transfers upon delivery at project site.