NET Power extends Saulsbury EPC notice-to-proceed deadline to March 31, 2027 from October 15
NET Power Inc.
- Agreement to Extend FNTP Date, effective Oct 15, 2026, pushes the full notice-to-proceed and Mobilization Payment deadline to March 31, 2027.
- Extension defers the $3.5M termination fee to Saulsbury only if the Fourth Amendment and a limited notice to proceed (LNTP) are executed and LNTP payments made by Nov 15, 2026.
- If those are not executed or paid by Nov 15, 2026, Net Power must pay Saulsbury $3.5M within 10 days of written demand and invoice.
- Net Power, LLC took over EMPower USA's Owner position under the Dec 15, 2025 Saulsbury EPC contract via an Aug 27, 2026 consent to assignment.
- Company cites no committed equipment or project-level financing, no final investment decision; EMPower consideration is nonrefundable and Wärtsilä equipment spend may not be recovered.