PureCycle revises construction milestones for Augusta PP recycling facility under CPA with AEDA
PureCycle Technologies, Inc.
- Company agreed to pay $500,000 in two $250,000 installments to AEDA; first due by Jan 9, 2026.
- Waived Phase II lease option for ~50 additional acres; Phase I site sufficient for second-gen lines.
- Revised timeline requires start of construction no later than March 2028; milestones extend through full production.
- Failure to meet milestones triggers penalties and termination rights in favor of AEDA.