Dominion Energy's CVOW cost rises to $11.5B; completion pushed to early 2027
DOMINION ENERGY, INC
- Estimated total project cost increased from ~$11.2B to ~$11.5B (excl. financing costs), driven by tariffs and work suspension.
- Completion now expected in early 2027, delayed from prior timeline.
- Work suspended Dec 2025 due to BOEM Director's Order; preliminary injunction issued Jan 2026 allowed resumption.
- Additional costs attributed to tariffs and the temporary suspension of work.