Contango Silver & Gold hits 62.97 g/t Au over 3.92 m at Lucky Shot; Phase 3 surface drilling complete
Contango Silver & Gold Inc.
- LSS26031 returned 62.97 g/t Au over 3.92 m, including 325.20 g/t over 0.73 m, below modeled Coleman 4; interpreted as a new vein.
- Phase 3 Coleman surface program completed about 5,800 m in 27 holes from five pads between June 22 and Aug. 31, 2026; LSS26028 returned 48.75 g/t over 0.30 m.
- Underground development is 606 of 830 planned meters complete, or about 73%; 29 holes totaling roughly 2,050 m have been drilled since Sept. 16, 2026.
- A second drill rig will mobilize for the 2300E drift; drilling is planned through February/March 2027, with an updated resource estimate targeted for late Q2 2027.
- The updated resource estimate and technical work are intended to support a Feasibility Study scheduled for H2 2027; no new underground assay results were reported.