Bit Digital closes $45M purchase of NC building for HPC data center; power ramp from Duke Energy
Bit Digital, Inc
- Acquired industrial building in Madison, NC for $45M (down from $53.2M); closed May 20, 2025.
- Duke Energy agreed to use commercially reasonable efforts for 24 MW by Sept 2025, 40 MW by Apr 2026, 99 MW within 4 years.
- Earnout: $8M if 99 MW secured within 2 years, $5M within 3 years; $200k/MW over 99 MW up to $5M additional.
- Property eligible for NC sales/use tax exemptions; local tax incentives under negotiation based on capex and job creation.
- Company used cash on hand; plans commercial mortgage financing for the site.
item 1.01item 2.01item 7.01item 9.01