Blockchain Digital signs 15-yr, 65 MW electric agreement at CLT-01; 25 MW LOIs in pipeline
BlockchAIn Digital Infrastructure, Inc.
- Expands contracted utility load from 40 MW to 65 MW under a 15-year term with existing 34.5 kV infrastructure – no major upgrades needed.
- Minimum monthly demand charge of $400,000; $200,000/month deferred without interest until Dec 31, 2027 or 40 MW demand reached.
- Customer pipeline includes letters of intent for 25 MW of committed IT load from a leading AI company and a financial institution.
- Power immediately available; first phase supports AI/HPC repositioning; new data center shell expected completed in nine months.