Digi Power X: AI data center on track for Dec 2026; targets $250-300M FY2027 run rate
Digi Power X Inc.
- Cash and cash equivalents ~$155M as of July 3, 2026; no long-term debt; YTD capex of $95M on Alabama site funded internally.
- Phase 1 of AI data center campus on track for ready-for-service Dec 2026; Phase 2 targeted for end of Q1 2027.
- NeoCloudz GPU-as-a-Service platform live with NVIDIA B200/B300 GPUs, generating first AI revenues in Q2 2026.
- FY2027 annualized run rate target of $250-300M: AI colocation $80-100M, GPUaaS up to $100M, energy sales ~$12M.
- US Data Centers' ARMS 200 modular unit live at Alabama facility since May 15, 2026, generating AI revenues.