Westlake plans full closure of Pernis facility; expects EUR 190M pre-tax costs
WESTLAKE CORP
- Plans to close entire Pernis facility (AC, ECH, LER, BPA units) in the Netherlands; consultations with works councils started June 13, 2025.
- Total pre-tax closure costs estimated at EUR 190M: EUR 30M severance for ~230 employees and EUR 160M environmental/shutdown costs.
- Substantially all charges expected in Q2 2025; cash outflows will extend over several years after closure.
- Will supply LER and BPA customers from Deer Park, Texas facility after Pernis shutdown.
- Previously mothballed AC and ECH units in July 2024; now entire facility cessation anticipated in 2025.