Ameresco updates SCE BESS project timeline; cites COVID lockdowns in China causing battery supply delays
Ameresco, Inc.
- COVID-19 lockdowns in China and new transportation safety policies may delay battery deliveries for three BESS projects with SCE.
- Ameresco invoked force majeure under the EPCM Agreement; completion date may extend without liquidated damages.
- Significant milestones achieved: transformers, inverters, switchgear secured; construction ongoing at all sites.
- No material impact on 2022 results expected; reaffirms annual earnings guidance issued Feb 28, 2022.
- Further updates expected with Q1 results in early May 2022.