Ameresco reaches agreement with SCE on substantial completion of two BESS projects; to receive ~$110M
Ameresco, Inc.
- SCE to pay ~$110M within 7 days for substantial completion milestone of two battery storage projects.
- Liquidated damages and force majeure claims remain disputed; Ameresco maintains LDs should not apply.
- Third BESS project significantly impacted by 2023 California rainfall; expected substantial completion in Q4 2024.
- Original guaranteed completion date was August 1, 2022; delays cited from supply chain, weather, and SCE instruction.