secwatch.observer — SEC 8-K summary ====================================== Issuer: Bunker Hill Mining Corp. (BHLL) CIK: 0001407583 Form: 8-K Filed at: 2024-12-18T23:59:59+00:00 Accession: 0001493152-24-050531 Event type: other_material Sentiment: negative Materiality: 0.75 Item codes: 7.01, 8.01, 9.01 LLM model: deepseek-v4-flash:cloud@v2 Bunker Hill mine restart cost rises to $103M, delayed to Q2 2025 ---------------------------------------------------------------- - Total restart expenditure (excl. working capital) now $103M, up from prior $67M and $56M (2022 PFS). - Project restart delayed by up to 4 months, now anticipated in Q2 2025. - Cost increase of ~$50M driven by inflation, filter press scope change, and contractor walk-out. - Plans to draw $5M first tranche from $21M Sprott standby facility; negotiating $30M offtake financing. - Pursuing $150M US EXIM facility by end of 2025 to refinance debt and expand capacity to 2,500 tpd. Source: EDGAR index: https://www.sec.gov/Archives/edgar/data/1407583/000149315224050531/0001493152-24-050531-index.htm Primary doc: https://www.sec.gov/Archives/edgar/data/1407583/000149315224050531/form8-k.htm HTML page: https://secwatch.observer/filing/0001493152-24-050531 License: Source filings: public domain (SEC EDGAR). Summaries (headline + bullets): CC-BY-4.0; attribute https://secwatch.observer