Stardust Power completes FEL-3 study for Oklahoma lithium refinery; Phase 1 capex ~$500M
Stardust Power Inc.
- Phase 1 capacity: 25,000 mtpa battery-grade lithium, expandable to 50,000 mtpa in Phase 2.
- Capital expenditure ~$500M for Phase 1, nearly $200M below prior estimates, with 90% probability.
- Construction timeline ~24 months from start of major work to mechanical completion.
- FEL-3 led by Primero USA; reduced contingency from 40% to lower level via 3D process model.
- Company advancing toward Final Investment Decision (FID) with independent third-party review engaged.