Soluna signs MOU with Metrobloks to co-develop 100+ MW AI/HPC data center at Project Kati 2
Soluna Holdings, Inc
- Initial 100+ MW Critical IT AI/HPC data center at Project Kati 2 campus; expansion to 300+ MW.
- Metrobloks leads design, leasing, operations; Soluna contributes site, power entitlements, equipment.
- Site under non-binding LOI from potential neocloud tenant; EDF Power to source additional wind power.
- Soluna broke ground on Project Kati in Sep 2025; Kati 2 is second phase for AI/HPC.