ERCOT conditionally classifies Soluna's 100 MW Project Dorothy as Base Load in Batch Zero
Soluna Holdings, Inc
- ERCOT conditionally classified Soluna's 100 MW Project Dorothy campus as Base Load in Batch Zero on Sept. 14, 2026.
- Follows conditional Base Load for 166 MW Project Kati; 266 MW across both Texas campuses are now conditionally classified.
- Company submitted load interconnection request for additional 50 MW at Dorothy; provider confirms study is underway.
- Project Dorothy is a 100 MW wind-powered campus at Briscoe Wind Farm (acquired April 2026); 98 MW of capacity is energized.
- Soluna's total operating capacity is ~206 MW with a ~6.3 GW pipeline; ERCOT queue holds ~438,000 MW, ~90% from data centers.