U.S. commits $249M to Port MacKenzie rail extension tied to Nova Minerals' planned Alaska antimony refinery
Nova Minerals Ltd
- Transportation Secretary Sean Duffy announced a $249M federal grant covering about 80% of the $311M, 32-mile Port MacKenzie Rail Extension; state and local partners supply the remaining $62M.
- Nova's planned antimony processing and refining hub sits directly on the extension with an on-site rail siding, linking Estelle ore and concentrate to the port.
- Duffy said the grant would move "at Trump speed," aiming to get funds out by spring and begin turning dirt; announcement made at Port MacKenzie on October 19, 2026.
- Related regional spending cited: $7.8M for port barge haul-out and loading capacity, $34M for port expansion, plus progress on the West Susitna Access Road serving Estelle.
- Nova says its antimony strategy is fully funded by a $43.4M U.S. Department of War award, with production targeted for 2027 in a domestic mine-to-end-user supply chain.