ADES signs GAC expansion contract; cost $45-50M, completion Q4 2024
Arq, Inc.
- Contract with Wieland-Davco on cost-plus basis; total construction and equipment cost estimated at $45-50M, up 20% from prior guidance.
- Mobilization underway; mechanical completion anticipated by Q4 2024; facility will add 25M lbs of granular activated carbon capacity.
- Corbin facility on track and within budget; commissioning activities begin March 2024.
- CEO expects to sign sales contracts for the 25M lb expansion well before Q4 2024 completion.