secwatch.observer — SEC 8-K summary ====================================== Issuer: TERAWULF INC. (WULF) CIK: 0001083301 Form: 8-K Filed at: 2026-10-05T12:21:35+00:00 Accession: 0001628280-26-064757 Event type: other_material Sentiment: positive Materiality: 0.62 Item codes: 8.01, 9.01 LLM model: deepseek-v4.1-flash:cloud@v2 TeraWulf doubles Muskie campus contracted power to 1 GW; second 500 MW phase moved up to 2029 -------------------------------------------------------------------------------- - DB Long Hunts Data LLC signed amended & restated transmission/energy agreements with Kentucky Power (AEP), lifting Muskie Data Campus contracted capacity from 500 MW to 1 GW. - Second 500 MW phase delivery advanced from 2030 to 2029, subject to Kentucky Public Service Commission approval; first 500 MW phase still targeted to ramp in 2028. - TeraWulf acquired Muskie in May 2026 for phased AI/HPC development and is evaluating the site for up to 2 GW over time; Kentucky Power is building a 765-kV/345-kV substation to serve it. - Financing strategy: intends to upsize its existing senior secured revolving credit facility and raise additional senior secured debt to support letter of credit needs. - Development proceeds under Gov. Beshear's Executive Order on Data Center Development (2026-494); Kentucky PSC in August approved the separate Justified Data Campus power agreement. Source: EDGAR index: https://www.sec.gov/Archives/edgar/data/1083301/000162828026064757/0001628280-26-064757-index.htm Primary doc: https://www.sec.gov/Archives/edgar/data/1083301/000162828026064757/wulf-20261001.htm HTML page: https://secwatch.observer/filing/0001628280-26-064757 License: Source filings: public domain (SEC EDGAR). Summaries (headline + bullets): CC-BY-4.0; attribute https://secwatch.observer