Soluna fully contracts Dorothy 2 with 30 MW expansion from top Bitcoin miner
Soluna Holdings, Inc
- 30 MW expansion with industry-leading Bitcoin miner; third expansion with same customer (initial deployment at Project Sophie in 2023).
- Project Dorothy 2 (48 MW data center co-located with 150 MW wind farm) now fully marketed and contracted.
- Expansion adds 1,462.03 PH/s hashrate from renewable energy; first phase online Q2 2025, full capacity Q4 2025.
- CEO John Belizaire says milestone brings 100% of active facilities to full capacity.