Soluna secures $20M from Spring Lane for Kati 1; pipeline grows to 2.8 GW
Soluna Holdings, Inc
- $20M secured from Spring Lane Capital to launch Project Kati 1; construction begins Q3 2025.
- Blockware expands to 8 MW at Dorothy 2; Compass Mining renews and expands to 13 MW campus-wide.
- Power pipeline increases 200 MW to 2.8 GW long-term capacity; contracting for Kati Phase 1 underway.
- Dorothy 2 (48 MW) construction on schedule; Phase 1 miner deployment imminent, Phase 2 power commissioning started.
- 30 MW partnership expansion at Dorothy 2 with existing customer; all 48 MW fully marketed for 2025.