Soluna completes Dorothy 2 Phase 2; secures $20M for Project Kati; $5M offering
Soluna Holdings, Inc
- Project Dorothy 2 Phase 2 construction substantially complete; customer ramp-up started; Phase 3 target completion Oct/Nov 2025.
- $20M secured from Spring Lane Capital for Project Kati 1 (first 35 MW); construction expected in Q3 2025.
- $5M public offering completed to strengthen balance sheet and support growth initiatives.
- Project Dorothy 2 now at full 48 MW hosting capacity with top-tier Bitcoin miner expansion.
- Pipeline of 2.8 GW continues expanding; tax abatement for Kati pending to begin construction.