Greenland Energy assumes farm-out role, extends Jameson wells to 2028, pays £500k
Greenland Energy Co
- March GL transfers all rights/obligations under Farm-Out Agreement to Greenland Energy Company.
- First and second exploration well longstop dates both extended to December 31, 2028 (from Dec 2026 and Dec 2027).
- Greenland Energy takes sole responsibility and cost for all drilling, environmental, and social permits for Jameson Project.
- Company pays 80 Mile plc £500,000 cash within 5 business days in consideration for the amendments.
- 80 Mile retains responsibility for other Government Consents and will provide reasonable assistance with permitting.