Net Power pauses first utility-scale project after FEED costs hit $1.7-2.0B, shifts to optimization
NET Power Inc.
- FEED for Project Permian completed; total installed cost estimated $1.7B-$2.0B, above viable threshold.
- Long-lead equipment releases paused; value engineering underway; project now expected no earlier than 2029.
- Launched modular multi-unit feasibility study for up to 1 GW plants to reduce future costs.
- La Porte facility achieved 140 fired hours in Phase 1 testing with Baker Hughes; on track for 2025 completion.
- Cash and investments at $533M (down from $580M Q3) used for La Porte upgrades and SN1 development.