PGE files updated final shortlist for 2023 All-Source RFP with OPUC, projects 1.0 GW capacity
PORTLAND GENERAL ELECTRIC CO /OR/
- Updated shortlist includes three projects: 250 MW solar+battery, 365 MW solar+battery hybrid, 400 MW battery (company-owned portions: 250, 175, 400 MW).
- Refresh triggered by July 4, 2025 passage of House Resolution 1 (One Big Beautiful Bill Act) and trade tariff impacts; bids re-evaluated with independent evaluator.
- OPUC acknowledgement sought by Nov 25, 2025; contract finalization expected by end of 2025, projects in service by end of 2027.
- PGE also pursuing renewable PPAs through bilateral all-call, community-based procurement, and ongoing 2025 RFP.