other material
confidence high
sentiment positive
materiality 0.50
Vaalco wraps Gabon Phase 3 as ETSEM-3H flows ~2,000 gross BOPD; Baobab Phase 5 drilling starts
VAALCO ENERGY INC /DE/
- ETSEM-3H development well in an attic position within Gabon's SE Etame field placed on production; 300 meters of net pay in Gamba reservoir sands.
- Stabilized initial flow rate of about 2,000 gross BOPD, or 1,140 BOPD net to Vaalco; Phase 3 drilling program now complete.
- Borr Norve rig demobilized from the SE Etame platform after the final Phase 3 well.
- Offshore Côte d'Ivoire, Baobab Phase 5 has begun with batch-setting of top-holes; plan calls for four producers, three water injectors and two workovers.
- First new Baobab producer expected online near end of 2026, with meaningful production growth anticipated in 2027, per CEO George Maxwell.