Fermi America Q3: 2.2GW gas secured, NRC accepts COL, IPO raises $785M
Fermi Inc.
- Secured 2.2GW gas-fired generation (surpassing 1.0GW target); first power delivery target remains end of 2026.
- NRC formally accepted COL application for four Westinghouse AP1000 reactors at Project Matador campus.
- Raised $1.6Bn YTD: $358M Macquarie-led private financing and $785M IPO at $21/share (32.5M shares).
- Executed $150M Advance in Aid of Construction Agreement with first investment-grade tenant for >1GW.
- Entered LOI with City of Amarillo for up to 10 MGD water; campus lease with Texas Tech University commenced.