TeraWulf doubles Muskie campus contracted power to 1 GW; second 500 MW phase moved up to 2029
TERAWULF INC.
- DB Long Hunts Data LLC signed amended & restated transmission/energy agreements with Kentucky Power (AEP), lifting Muskie Data Campus contracted capacity from 500 MW to 1 GW.
- Second 500 MW phase delivery advanced from 2030 to 2029, subject to Kentucky Public Service Commission approval; first 500 MW phase still targeted to ramp in 2028.
- TeraWulf acquired Muskie in May 2026 for phased AI/HPC development and is evaluating the site for up to 2 GW over time; Kentucky Power is building a 765-kV/345-kV substation to serve it.
- Financing strategy: intends to upsize its existing senior secured revolving credit facility and raise additional senior secured debt to support letter of credit needs.
- Development proceeds under Gov. Beshear's Executive Order on Data Center Development (2026-494); Kentucky PSC in August approved the separate Justified Data Campus power agreement.