Tri-State enters $195.6M EPC contract for 145 MW solar project in Colorado
Tri-State Generation & Transmission Association, Inc.
- Turnkey EPC contract with JSI Construction Group for 145 MW AC solar facility in Moffat County, Colorado.
- Total contract price of $195,611,863, payable via milestone schedule; first payment due upon notice to proceed.
- Project expected to achieve commercial delivery by December 31, 2025; liquidated damages for delay.
- Notice to proceed to be issued by June 1, 2024; EPC contractor responsible for full construction except transformer.
- Tri-State separately acquiring project assets from Axial Basin Solar LLC via Asset Purchase Agreement dated same day.