New Fortress Energy's Fast LNG unit offline after gas turbine mechanical failure; Q4 return targeted
NFE said its Fast LNG unit is offline following a mechanical issue with the facility's gas turbine, disclosed in the Oct. 5, 2026 filing.
-
NFE completes $6.18B debt restructuring; splits into CoreCo, BrazilCo; pro forma equity turns positive
Completed restructuring of ~$6.18B funded debt via UK Part 26A plans; High Court sanctioned June 18, 2026; effective Sept 11, 2026
-
New Fortress Energy completes comprehensive debt restructuring, splits into BrazilCo and CoreCo
On Sept 11, 2026, NFE consummated restructuring; creditors received 100% of BrazilCo equity, $571.3M new CoreCo term loans, and 10.6M common shares (65% of CoreCo).
-
New Fortress Energy CFO Christopher Guinta resigns, effective Aug. 21, 2026
Christopher S. Guinta announced resignation as CFO on Aug. 17, 2026, effective Aug. 21, 2026.
-
NFE Brazil subsidiary issues $973.5M of 12% senior secured notes due 2029
Issued $973.5M aggregate principal amount of 12.000% Senior Secured Notes due November 15, 2029.
-
New Fortress Energy shareholders approve 1-for-50 reverse split, charter amendments in restructuring
Stockholders approved a 1-for-50 reverse split of Class A common stock with 221,585,026 votes for.
-
New Fortress Energy receives UK court approval to convene creditor meetings on restructuring plan
High Court granted convening order on May 14, 2026 for Plan Companies to hold creditor meetings.
-
NFE subsidiary commits to $885M senior secured notes at 12% PIK; part of Brazil separation
$885M aggregate principal of senior secured notes due 2029, 12.00% PIK interest, no call protection or financial covenants.
-
New Fortress Energy receives Nasdaq delisting notice for bid price below $1.00
Received Nasdaq notice on May 1, 2026 for closing bid price under $1.00 for 30 consecutive days.
-
New Fortress Energy closes $265.9M turbine sale-leaseback with Macquarie
Sold turbines to Macquarie Energy LLC for $265,882,500; net proceeds used to repay indebtedness.
-
New Fortress Energy enters forbearance until Sept 15, 2026 on Letter of Credit facility
Forbearance agreement with lenders under July 2021 Letter of Credit Agreement signed March 27, 2026.
-
New Fortress Energy extends credit maturity to Sep 2026, waives defaults
Entered 14th Amendment on March 19, 2026 extending Letter of Credit maturity to September 15, 2026.
-
New Fortress Energy restructuring: debt-for-equity swap, spin-off Brazil assets, shareholder dilution
Comprehensive debt restructuring of ~$5.7B in principal claims via exchange for equity and new debt.
-
NFE restates prior financials; enters restructuring support agreement with creditors
Restates FY2024, FY2023, and interim 2024/2025 financials due to cash flow misclassification of delayed vendor payments.
-
New Fortress Energy misses debt payments, enters forbearance agreements through Jan 9, 2026
Missed ~$30.6M TLB interest payment due Dec 10; event of default occurred Dec 17 after grace period expiration.
-
NFE extends forbearance on 12% notes to Jan 9; amends LC facility to keep $195M commitments
Forbearance period on 12% Senior Secured Notes due 2029 extended from Dec 15 to Jan 9, 2026.
-
NFE amends L/C agreement to extend maturity, impose restrictions; failure of forbearance could trigger defaults
Eleventh Amendment to Letter of Credit Agreement extends maturity to March 31, 2026.
-
NFE reports Q2 net loss $557M; Adjusted EBITDA -$4M; initiates strategic alternatives review
Net loss of $557M ($2.02 diluted EPS) vs. $86.9M loss a year ago; revenue $301.7M, down 29% YoY.
-
NFE receives Nasdaq delisting notice for late Q2 2025 10-Q filing
Received Nasdaq notice on Aug 19, 2025 for failure to timely file Form 10-Q for period ended June 30, 2025.
-
NFE Q1 net loss $197M, operating cash flow -$32M; late filing persists
Net loss of $197.4M in Q1 2025 vs net income $56.7M in Q1 2024; operating cash flow -$31.7M.
-
New Fortress Energy receives Nasdaq delisting notice for late Q1 2025 10-Q
Nasdaq notice for failure to file Q1 2025 Form 10-Q by May 20, 2025.
-
NFE closes $1.055B sale of Jamaica LNG business to Excelerate Energy; repays $279M debt
Closed sale of Jamaica assets (Montego Bay terminal, Old Harbour FSRU, 150 MW CHP plant) for $1.055B cash on May 14, 2025.
-
NFE completes $1.055B Jamaica sale to Excelerate; Q1 net loss $197M, Adj EBITDA $82M
Closed sale of Jamaica assets to Excelerate Energy for $1.055B; proceeds to reduce corporate debt.
-
New Fortress Energy amends credit agreements ahead of Jamaican asset sale; raises rates, adds covenants
Twelfth Amendment waives 75% asset sale prepay rule; allows $270M of sale proceeds to extend RCF tranche due Sept 30, 2025.
-
NFE sells Jamaica LNG assets to Excelerate Energy for $1.055B cash
Excelerate to acquire NFE's Montego Bay LNG terminal, Old Harbour FSRU, and 150 MW Clarendon power plant.
-
New Fortress Energy secures $1.27B in term loans to fund FLNG2 capex; existing TLA commitments reduced to zero
Second Amendment permits $425M incremental term loans plus exchange of $847.44M existing loans for new $1.272B total.
-
NFE beats Q4 EBITDA guidance; reports net loss on debt refinancing; Fast LNG in service
Adjusted EBITDA Q4 $313M (beat $200-220M guide); full year $950M (beat $835-855M).
-
Holders convert 35,000 Series B Preferred shares; NFE issues 3.88M common shares with 6.9M more possible
On Jan 6, 2025, holder converted 20,000 Series B Preferred shares, requiring delivery of 2,208,612 common shares by Jan 21, 2025.
-
NFE closes $1.52B second tranche of 12% notes, issues 15.7M shares as fee
NFE Financing issued $1.520B aggregate principal of 12.000% Senior Secured Notes due 2029 to supporting holders on Dec 6, 2024.
-
NFE issues $1.2B of 12% Senior Secured Notes due 2029; redeems $875M 6.75% Notes due 2025
Issued ~$1.207B aggregate principal of 12% Senior Secured Notes due Nov 2029; net proceeds ~$1.2B.
-
New Fortress Energy amends credit facility; PortoCem unit plans R$4.5B debenture issuance
Second Amendment to credit agreement pledges equity in certain Unrestricted Subsidiaries and excludes Brazil assets from Excluded Assets.
-
NFE Q3 Adjusted EBITDA $176M, matches guidance; refinances $2.7B debt, raises $400M equity
Q3 revenue $567.5M, net income $11.3M ($0.03 EPS); Adjusted EPS $0.05.
-
NFE enters $2.7B debt restructuring: $1.2B subscription + $1.5B exchange of 12% notes due 2029
Issued $1.2B in new 12% Senior Secured Notes due 2029 via subscription and $1.5B via exchange for existing 6.5% and 8.75% notes.
-
New Fortress Energy raises ~$387M in stock offering, issues Series B Preferred to Ceiba
Underwritten public offering of 46,349,942 shares at $8.63 each; net proceeds ~$387.25M.
-
New Fortress Energy enters TSA to issue $1.2B 12% notes, exchange $1.4B notes, raise $250M equity
New Fortress Energy enters TSA with noteholders to refinance existing 2025/2026/2029 notes; issues $1.2B new 12% senior secured notes due 2029.
-
NFE prices $400M public offering at $8.63/share; CEO Edens buys 5.8M shares
46.35M shares of Class A common stock priced at $8.63/share for gross proceeds of ~$400M.
-
New Fortress Energy expects $150-200M in gross proceeds from sub-chartering below-market vessel charters
Company has long-term vessel charters with Energos currently below market; may sub-charter vessels not needed.
-
NFE delays dividend, faces tight liquidity; credit amendments require $250M equity raise by Oct 7
Credit amendments require $250M equity raise and $300M+ debt refinancing by Oct 7, 2024 to maintain covenant suspension.